Issue: Lithotriper Utilization
Conclusion: Veterans Health Administration (VHA) can reduce lithotripsy costs by improved management of existing units and realignment and consolidation of resources.
Impact: $2.73 million potential Better Use of Funds.
We audited the use of lithotripters in VHA to determine if existing
lithotripsy units were operating economically and efficiently,
and were sufficient to meet VHA's workload. Lithotripters are
used to crush kidney and urinary tract stones with shock waves
and cost between $725,000 and $1.9 million each. We found that,
in Fiscal Year (FY) 1995, the 12 VA medical centers (VAMCs) with
VA-owned lithotripters performed only 1,626 procedures, about
11 percent of total capacity. We concluded that additional capacity
is not needed. We recommended realignment and consolidation of
lithotripsy capability by designation of six lithotripsy resource
centers, closure of other lithotripsy suites as equipment becomes
obsolete, and cancellation of any planned lithotripsy suites.
We also recommended several actions to reduce lithotripsy operating
costs, including providing treatment on an outpatient basis, whenever
possible; using in-house maintenance; and improving contract administration
over shared resources. These recommendations could result in
a savings of $2.73 million.
The Under Secretary for Health provided an acceptable alternative
to our realignment proposal, tasking the Network Clinical Managers
to assess various options in obtaining lithotripsy services, including
selling excess capacity and increasing the use of contracts for
community services. The Under Secretary also agreed to develop
guidelines for best practices in managing lithotripter units,
and canceled two planned lithotripsy suites, with the cancellations
estimated to result in a $2.2 million better use of funds. We
consider all issues in the report resolved. (Audit of Lithotripter
Utilization)
Issue: Use of Intergovernmental Personnel Act (IPA) Assignments
Conclusion: VHA needs additional policy guidance to help ensure the appropriate use of IPA assignments.
Impact: $1.3 million potential Better Use of Funds.
This audit was conducted as part of our ongoing review of affiliation
issues. IPAs are used to temporarily obtain skilled personnel,
with VAMCs the largest users, primarily to obtain medical school
employees on a temporary basis to work on research projects.
In FY 1996, we estimated that VAMCs had over 1,000 IPA agreements
in use at a cost of over $34 million.
We first reviewed use of IPAs at one VAMC, the largest user of
IPAs, and expanded the review to two other VAMCs. At all three
VAMCs, we found IPA use to support research activities was in
compliance with IPA regulations, but IPAs were inappropriately
used to obtain clinical services and for administrative and support
positions. In addition, the largest user did not have adequate
controls to prevent IPA overpayments, with excessive payments
estimated at $1.3 million annually. Based on our initial findings,
the Under Secretary for Health initiated immediate action by issuing
a reminder to VHA field facilities which outlined the purpose
of IPA assignments and emphasized the need for compliance with
IPA regulations. He also agreed with our recommendation to issue
detailed guidance on the use of IPA assignments. Based on these
actions, we terminated the planned nation-wide review. (Audit
of VAMC Use of IPA Assignments)
Issue: Prescribing Practices for Elderly Outpatients
Conclusion: VHA can help optimize medication management for specific drugs and patient populations by providing data on drug specific prescribing practices to VHA managers and clinicians.
Impact: Medication management for elderly veterans improved.
We conducted a review of VHA's prescribing practices for selected
drugs issued to outpatients aged 65 or older. The purpose of
the review was to help VHA: (i) assess how well it manages certain
medications for the elderly, and (ii) develop management tools
for health care providers to monitor and optimize medication management
for the elderly.
Studies published in The Journal of the American Medical Association
(JAMA) in 1994 and by the General Accounting Office (GAO) in 1995
concluded that between 17.5 and 25 percent of noninstitutionalized
elderly patients were taking one or more of 20 prescription drugs
that many experts regard as generally unsuitable for their age
group.
Our review focused on 4 of the 20 drugs reported in JAMA and by
the GAO. Based on a nation-wide review of prescribing practices
for these four drugs, we found that, during the first 6 months
of FY 1996, VHA providers prescribed these four drugs to elderly
outpatients substantially less frequently than non-VA providers
as reported in both the 1994 JAMA article and the 1995 GAO report.
During our review at one VAMC, we found that by providing VAMC
managers and clinicians information regarding their prescribing
practices for these drugs, prescribing practices changed to further
improve medication management for elderly patients. We recommended
that VHA provide information regarding prescribing practices to
all VHA facilities and to incorporate automated data processing
applications developed for the review into the national Decentralized
Hospital Computer Program system. The Under Secretary for Health
concurred with the findings and recommendations and provided acceptable
implementation plans. We consider all issues resolved. (Review
of Prescribing Practices for Elderly Outpatients)
Issue: Geriatric Research, Education, and Clinical Centers (GRECC) Program
Conclusion: The GRECC program is meeting its mission to improve care to elderly veterans, but services could be enhanced further by establishing GRECC-developed treatment models and educational programs at more VA facilities.
Impact: Expansion of programs for elderly veterans to other facilities.
We evaluated the effectiveness of VA's GRECC program in meeting
the needs of elderly veteran patients. Annual GRECC program
costs total approximately $24 million. During FY 1995, funding
for research totaled $77 million. We concluded that the GRECC
program was meeting its mission, and recommended that the Under
Secretary for Health develop a method for establishing GRECC-developed
treatment models and educational programs at more VA facilities.
The Under Secretary for Health concurred with our conclusions
and recommendation and provided an acceptable implementation plan.
(Audit Of Department of Veterans Affairs GRECC Program)
Issue: Financial and Management Oversight of the Home Improvement and Structural Alterations (HISA) Program
Conclusion: VA should define allowable HISA services, better identify eligible veterans for the program, and strengthen financial management.
Impact: Improved program for disabled veterans.
We initiated this audit at the request of the Under Secretary
for Health to evaluate the financial and management oversight
of the HISA program. The HISA program was established in October
1976 to assist veterans who needed home improvements or structural
alterations to provide accessibility to the home or ensure continuation
of treatment in the home, rather than in a hospital or nursing
home. HISA program costs increased from $1.9 million in FY 1991
to over $4 million in FY 1996. Overall, the program was accomplishing
its intended purpose of allowing veterans better access to their
homes. We made recommendations to improve the definition of eligible
projects/ services, and to improve financial management of the
program. The Under Secretary for Health concurred with the recommendations
and provided acceptable implementation plans. We consider all
audit issues resolved. (Audit of the HISA Program)
Issue: Advance Directives for End-of-Life Decisions
Conclusion: The VHA has aggressively pursued and supported patients' rights to decide the extent to which VHA clinicians should attempt to prolong their lives in the final stages of illness.
Impact: Improved procedures.
In November 1991, VHA implemented a Living Will/Advance Directive
program to facilitate patients abilities to direct their care.
The term, Advance Directive, refers to competent adults' specific
oral and written statements as to their desires for withholding
or withdrawal of life-sustaining treatments. We conducted a review
to evaluate VHA's efforts to ensure that patients have the opportunity
to dictate the measures that clinicians will take to prolong their
lives in the final stages of terminal illnesses.
We found that VHA clinical employees closely adhere to the guidance
and philosophy that patients have a right to decide on this important
issue, that they take every reasonable action to keep patients
comfortable, and/or provide procedures that alleviate pain and
suffering before the end-of-life events occur. In certain cases,
lacking patients' future ability to make these decisions, the
patients may appoint family members as surrogates to make the
decisions for them. We found that employees consistently adhere
to surrogates' wishes as well. We found that social workers are
in the vanguard of discussing these issues with patients and their
family members. We also found that VHA's advance directive forms
are written in complex language that exceeds the average VA patients'
reading ability, and this many times intimidates patients and
their families to the extent that they are reluctant to initiate
the advance directive actions. We recommended that physicians
become more involved with counseling patients at the appropriate
times. We also encouraged the Under Secretary for Health to consider
revising existing guidance that allows employee counseling on
this issue only after the patient is hospitalized such that employees
may initiate the discussions while the patient is in an outpatient
setting, and is less intimidated by the environment.
The Under Secretary for Health concurred in our recommendations
and implemented or planned appropriate actions to strengthen advance
directive procedures. (Evaluation of the VHA's Advanced Directive
Program)
Issue: Nation-wide Quality Program Assistance (QPA) Reviews
Conclusion: VAMC top managers were individually and collectively involved in several actions that were focused on ensuring that eligible veterans have access to high-quality, low-cost health care.
Impact: Advisory report.
We conducted a QPA review at VAMC Durham, as part of our QPA development
process. The QPA process is intended to add value to other external
review activities that oversee VHA facilities. Review instruments
assess the extent to which VHA's four performance goals: (i) cost-efficient
care, (ii) high quality care, (iii) improved patient access to
care, and (iv) improved patient satisfaction, are being met.
We concluded that the VAMC's top managers were individually and
collectively involved in several actions that were focused on
ensuring that eligible veterans have access to high quality, low
cost health care. In addition, mid-level managers and operating
employees were aware of, and supported management's treatment
goals, and patients indicated that they were generally pleased
with the care they received. (Quality Program Assistance Review,
VAMC Durham, NC)
Issue: Medical School Affiliations
Conclusion: VHA continues to make progress on affiliation issues and should pursue the renegotiation of affiliation agreements and avoid special arrangements.
Impact: Additional efforts to strengthen affiliations.
This report summarizes the results of 16 OIG audits of affiliation-related
activities conducted over the past 4 years, and Office of Audit
observations of affiliation issues. Each year, more than 100,000
residents and students receive all or part of their training at
VA facilities. In FY 1995, VA spent about $1.5 billion to directly
or indirectly support affiliation activities. This included funding
of about 8,900 medical resident positions at an estimated cost
of $341 million. This means that VA supported about 9 percent
of the medical residents in the United States. About 75 percent
of VA's 173 medical centers are affiliated with medical school
faculty appointments.
We found that VHA management had taken actions to respond to our
specific recommendations and had made significant progress in
addressing the issues of management of physician resources, contractual
relationships with medical schools, and management information
and resource allocation systems. To continue momentum in improving
medical school affiliations, we recommended that VHA: (i) remind
VAMC and network officials that they must avoid questionable special
arrangements with affiliates, and (ii) pursue renegotiation of
affiliation agreements.
The Under Secretary for Health concurred in the findings and recommendations
and indicated that the report accurately reflected VHA's ongoing
efforts to strengthen affiliation relations. VHA's implementation
plan was acceptable, and we consider all issues to be resolved.
(Summary Report: Audits of VA Medical School
Affiliation Issues)
Issue: Alleged Inadequate Anesthesiology Quality Management Procedures
Conclusion: A lack of adequate monitoring of anesthesiology procedures compromised managers' ability to know if patients were receiving consistently high quality care.
Impact: Anesthesiology quality management procedures established.
We reviewed allegations of multiple administrative and clinical
deficiencies involving anesthesia operations at VAMC Richmond.
Several patients had reportedly been harmed by improperly performed
anesthesia and cardiac surgical procedures, equipment failures
reportedly resulted in patient injuries, and Anesthesiology Service
allegedly did not have adequate quality management procedures
in place to identify and evaluate these incidents or to correct
the problems that allowed them to occur.
We found that several patients had experienced untoward or unwanted
events during the course of their treatment in the operating room.
Anesthesiology Service did not have procedures in place to identify
and monitor the types of events that occurred, and the Service
chief did not have any way of evaluating or correcting staff performance
on a continuing basis. We also found, however, that Surgical Service
had a highly effective quality management monitoring and tracking
system, and all of the cases that the complainant raised had been
discussed in the context of Surgical Service staff meetings.
In addition, corrective actions had been initiated to reduce the
possibility that similar incidents would recur. The review also
found that operating room employees had not reported malfunctions
of emergency equipment because they interpreted Department policy
to mean that incidents that occurred in the operating room were
to be managed and corrected by operating room staff.
We concluded that lack of an anesthesiology quality management
process provided an environment in which improper anesthesia treatment
practices could occur without being detected or corrected, and
that inconsistent reporting of patient incidents in the operating
room inhibited medical center managers' ability to identify equipment-related
malfunctions, and correct them in a timely manner. The medical
center director took appropriate actions subsequent to our inspection
to correct the identified problems. (Inspection of Selected
Clinical and Administrative Issues on Anesthesiology Service,
Hunter Holmes McGuire VAMC Richmond, VA)
Issue: Alleged Release of a Potentially Dangerous Patient from Inpatient Care
Conclusion: Medical center clinicians properly evaluated and treated the patient.
Impact: Assurance of proper care to a veteran.
We reviewed a family's concerns that medical center clinicians
had not properly evaluated a patient's potential for committing
violent acts, and that their proposal to discharge a patient from
care threatened the family's safety and security. We found that
the patient had been admitted to the medical center on a court
order because of homicidal and suicidal ideations. He had a lengthy
hospitalization, was no longer subject to a court order, was being
housed in the domiciliary, and could leave the hospital grounds
of his own free will. Because he was not under a court order,
clinicians had no legal right to keep him in the hospital. In
addition, the patient's brother had requested his release to live
with him and his family, and had assured clinicians of ongoing
monitoring, including followup in a mental health clinic. The
patient had left the medical center and traveled to his brother's
home without incident. We concluded that clinicians had carefully
and thoroughly monitored and evaluated his condition and behaviors.
No recommendations were made. (Inspection of Alleged Premature
Discharge of a Potentially Violent Patient From a Psychiatric
Unit at the Franklin Delano Roosevelt VA Hospital Montrose, NY)
Issue: Alleged Clinical and Administrative Mismanagement
Conclusion: Patient care met or exceeded accepted standards; lack of trust between employees and their patients and family members lowered morale, and made employees unsure of how to treat their patients.
Impact: Team building program established to improved morale/ services.
We reviewed allegations that managers at VAMC Prescott had failed
to address serious concerns about patient abuse, theft of patients'
valuables, and various administrative deficiencies on the nursing
home care unit (NHCU). In addition, managers had allegedly covered
up these issues and therefore staff could not trust them to correct
other identified problems. Inspectors found that managers had
conducted several administrative investigations and preliminary
inquiries into each of the employees' allegations, and they had
implemented several actions to correct the problems. They rightfully
had not communicated all of their actions to the employees, and
not all of the corrective actions were apparent. Specifically,
managers had conducted a comprehensive investigation into charges
of patient abuse, and an employee was terminated as a result of
the investigative findings. In addition, another employee was
arrested by OIG investigators for stealing a NHCU patient's funds
and diverting them to her own use.
Inspection concluded that these high-profile incidents had shaken
employees' confidence in their ability to properly treat their
patients without being charged with ethics violations, and had
shaken their trust in their fellow employees as well. In addition,
there was a mutual distrust between employees, and patients and
their families based on these high-profile incidents. The inspection
also found that medical center clinical service chiefs did not
include NHCU clinicians in routine staff meeting deliberations,
so clinicians felt alienated from their colleagues; and the recruitment
of volunteers for NHCU assignments could potentially provide a
degree of latitude for employees to divert time from direct patient
care activities to the extent that they could provide more personalized
services to their patients.
We recommended that the Director initiate team building and confidence
building for the NHCU staff, and that clinical service chiefs
be encouraged to bring their NHCU-based employees into the mainstream
of their respective staffs. We also recommended that the Director
encourage the Chief of Voluntary Service to work with NHCU nursing
managers to develop statements of meaningful work that regularly
scheduled volunteers would find interesting, and that the Chief
of Voluntary Service recruit interested volunteers to staff these
positions. The Director took immediate action to implement the
recommendations. (Inspection of Alleged Patient Abuse and
Substandard Patient Care on the NHCU, VAMC Prescott, AZ)
Issue: Investigation of Patient Death
Conclusion: The patient was murdered.
Impact: Unusual incident with no VA-wide implications.
An individual who was a patient at a VAMC was convicted of first
degree murder in the death of a second patient following a jury
trial in U.S. District Court. Initially, it was believed that
the victim had suffered fatal injuries after falling down a flight
of stairs. However, a joint investigation conducted by the OIG
and the Federal Bureau of Investigation revealed that he had suffered
multiple injuries to the head caused by a blunt instrument and
had defensive wounds to his hands. The individual faces a mandatory
life sentence.
Issue: Illegally Obtained Drugs
Conclusion: Investigations disclosed fraudulent acts by individuals to obtain drugs.
Impact: Individuals are held accountable for illegal acts.
Issue: Investigation of Suspected Fraudulent Claims
Conclusion: Individual submitted false invoices for services not provided.
Impact: Individual is held accountable for illegal acts.
A physical therapist, who provided services to veterans under VA's fee-basis program, entered into a settlement agreement with the Department of Justice requiring the therapist to make monetary restitution to the Government. A proactive OIG investigation of fee basis fraud disclosed that the therapist submitted false invoices to VA for home-based healthcare services to veterans which he did not provide.
Issue: Compensation and Pension (C&P) Overpayments
Conclusion: Veterans Benefit Administration (VBA) can further enhance overpayment prevention efforts and reduce program costs.
Impact: $30.4 million potential Better Use of Funds.
We reviewed the causes of C&P overpayments valued at $120
million outstanding as of the end of FY 1995. Overpayments occurred
when beneficiaries received money to which they are not entitled,
generally as a result of changes in their entitlement status (income,
dependency, hospitalization status, or death).
We estimated that overpayments valued at $26.2 million could be
prevented annually if VBA policy and procedures are revised and
cases are properly processed. C&P overpayments could be further
reduced by $4.2 million annually, if the program is simplified
and beneficiaries timely report beneficiary status changes.
We recommended that VBA reduce C&P overpayments by: (a) directing
VA regional office (VARO) staff to make overpayment prevention
a continuous special focus area of their quality reviews; (b)
gathering and disseminating innovative best practices that help
prevent overpayments; (c) revising due process notification procedures
for veterans receiving long-term care, fiduciaries of incompetent
veterans, dependent school children, and for beneficiaries reporting
status changes that result in a reduction of benefits; (d) revising
procedures for certain cases involving direct deposit of benefit
payments; and (e) encouraging VAROs to enlist the assistance of
veterans services organizations to improve timeliness of status
changes reported by beneficiaries.
Management is addressing the issue of overpayments as part of
their National Performance Review and Business Process Reengineering
initiatives. We also noted that VAROs have implemented innovative
procedures to prevent overpayments. The Acting Under Secretary
for Benefits concurred with the findings and recommendations and
provided an acceptable implementation plan. Actions on our recommendations
involving revision of due process procedures were considered consistent
with current statutory, regulatory, and judicial requirements.
(Review of the Causes of VBA's C&P Overpayments)
Issue: Invested Funds for the Servicemen's Group Life Insurance (SGLI) and Veterans' Group Life Insurance (VGLI) Programs
Conclusion: VA needs more financial information in order to better supervise administration of invested insurance funds.
Impact: $3.8 million potential Better Use of Funds.
The SGLI and VGLI are programs supervised by VBA and administered
by a major insurance company, hereafter referred to as the Insurer.
The Insurer reported $32 million and $40 million of program earnings
from investments, respectively, during calendar years 1993 and
1994. We audited the administration of invested funds for the
SGLI and VGLI programs to assess the accuracy, reliability, and
sufficiency of the Insurer's financial information.
We found that investment expenses were deducted from income, and
that funds were transferred to the Insurer without being reported
to VA. Although the governing legislation and provisions of group
insurance policy did not require the Insurer to report this information
to VA, its absence impeded VA management's ability to fully assess
the accounting of invested funds and program reserves, and determine
whether program investment earning could be enhanced. As a result
of the audit, the Insurer agreed to a restoration of $3.8 million
to invested assets and a reimbursement of lost income to the SGLI
and VGLI programs' reserve of $3.2 million.
We recommended that VBA determine whether the Insurer's estimates
of previous interbranch charges to program funds, including those
described as "Dividends to Stockholder", are reasonable
and whether the Insurer's proposed $3.8 million restoration to
invested assets and $3.2 million reimbursement to program reserves
are equitable. We further recommended that the Director, Insurance
Service obtain more information about program financial operations,
verify the accuracy of the insurer's accounting of SGLI and VGLI
investment funds, clarify the Insured's equity in program funds,
and assess whether opportunities exist to enhance program earnings.
The Under Secretary for Benefits concurred with the recommendations
and provided an acceptable implementation plan. (Administration
of Invested Funds for the SGLI and VGLI Programs)
Issue: Waiver Decisions For C&P Debts
Conclusion: Improvements in the quality and uniformity of waiver decisions are needed.
Impact: $2.9 million potential Better Use of Funds.
We conducted a review to evaluate the quality of decisions to
waive the collection of C&P debts, and to assess Committee
on Waivers and Compromises (COWC) program policies and operating
procedures. During FY 1995, VBA waived beneficiary debts to VA
valued at about $67 million. Our review covered COWC operations
during FY 1995 and the first half of FY 1996.
We conducted a stratified statistical analysis on debts valued
at $11.6 million and found waiver decisions in 30 percent of the
debt cases reviewed were not supported by the evidence of record.
Based on our sample results, we estimated that decisions to waive
debts valued at $2.9 million were questionable. We also found
a wide variance in decision results among the VAROs, with individual
VAROs granting from 27 percent to 5 percent of waiver requests.
We found that 11 VAROs granted waivers for over 70 percent of
the cases, while 7 VAROs granted waivers in under 40 percent of
the cases. The variance demonstrates a difference in the application
of waiver criteria and results in unequal treatment of similarly
situated beneficiaries who submit waiver requests.
We recommended that the Acting Under Secretary for Benefits improve
the quality of decisions by enhancing guidance, conducting training,
requiring more thorough quality reviews of waiver cases, and increasing
VA Central Office oversight of the program. The Acting Under
Secretary for Benefits concurred with the report recommendations
and provided acceptable implementation actions. We considered
all issues resolved. (Review of Waiver Decisions for C&P
Debts)
Issue: Data Reliability in the Claims Processing Workload Reporting System
Conclusion: Reliability of data in VBA's claims processing workload reporting system can be enhanced and opportunities exist to use beneficiary demographic data to estimate future workload requirements.
Impact: Increased accuracy and reliability of data.
We audited data reliability in the workload reporting system at
the request of VBA's Chief Financial Officer because of concerns
that data were not sufficiently accurate to assure appropriate
workload reporting and performance measurement of VBA operations.
We identified opportunities for VBA to enhance the accuracy and
reliability of workload reporting and performance measurement
of claims processing operations, which can result in improved
tracking of the delivery of benefits to beneficiaries. We also
identified opportunities to use demographic data on beneficiaries
derived from the C&P automated files as a tool to enhance
predictions of future workload. The Acting Under Secretary for
Benefits concurred with our recommendations, and provided acceptable
implementation actions. We consider all issues resolved. (Audit
of VBA's Data Reliability in the Claims Processing Workload Reporting
System)
Issue: Fraud in Loan Guaranty Program
Conclusion: The Loan Guaranty Program remains vulnerable to fraud involving loan origination.
Impact: Individuals are held accountable for illegal acts.
Issue: Integrity of Beneficiary Programs
Conclusion: Fraud continues in pension, compensation, and fiduciary programs.
Impact: Individuals are held accountable for illegal acts.
Pension Fraud
Compensation Fraud
Fiduciary Fraud
Issue: Contractor Overcharges for Drugs, Medical Equipment and Supplies
Conclusion: Contract reviews disclosed contractor overcharges.
Impact: VA will recover over $4 million, with the potential for significant additional FY 1997 recoveries.
As a result of VA team efforts during the period, the VA will
recover $4 million in contract overcharges on several Federal
Supply Schedule (FSS) contracts. In addition, we have work in
process on several additional significant recoveries. Recoveries
from contractors represent the collective efforts of the Office
of Acquisition and Materiel Management, the Office of General
Counsel (OGC), VHA, and the OIG working as a team to produce these
results.
Issue: Contractor Overpricing on Utility Services' Proposal
Conclusion: VA fixed costs for chilled water were overpriced.
Impact: $835,730 potential Better Use of Funds.
We reviewed a contractor's proposal for a 35-year contract, with
proposed costs of approximately $17.4 million, to provide chilled
water for air conditioning at a VAMC. The proposal was submitted
by an affiliated health care provider under an exchange of use
agreement with the VAMC. The agreement provided that VA would
furnish the equipment and the contractor would construct and maintain
a chilled water plant and operate the plant. Our review determined
that the proposal was overpriced due to excessive fixed costs
and we recommended that the contracting officer negotiate a reduced
price. The contracting officer agreed with the recommendation
and was able to negotiate reduced costs, projected to be $835,730
over the life of the contract.
Issue: VAMC Sharing Agreement with Medical School
Conclusion: VAMC was not paid for medical services provided.
Impact: VA recovered approximately $1.4 million.
A prior audit of a sharing agreement at a VAMC resulted in an
OGC opinion that the affiliated medical school was legally obligated
to pay VA for medical services provided to it from 1985 until
1990, which had not already been paid for by Medicare or the medical
school. The medical school disputed the decision. During this
reporting period, the case was settled for $850,000, and together
with sums previously collected, VA recovered approximately $1.4
million.
Issue: VA's Excess Equipment Program
Conclusion: VA can enhance the financial benefits, controls, and reporting associated with its excess equipment program.
Impact: $5 million potential Better Use of Funds.
We conducted an audit to assess the efficiency and effectiveness
of VA's disposal of excess and surplus personal property at the
request of the Office of Acquisition and Materiel Management.
For FY 1995, VA reported to the General Services Administration
(GSA) that personal property originally costing $82
million had been determined to be excess to program needs and
had been transferred directly to other federal agencies, scrapped,
abandoned, destroyed, or sold. VA also reported that personal
property originally costing $49 million had been traded-in or
sold pending replacement with like items. Proceeds from VA sale
of this property in FY 1995 totaled less than $6 million with
an additional $4.5 million in sales by GSA and $3.4 million in
trade-in allowances.
We concluded that the excess equipment program can be more effectively
managed by: (i) ensuring that guidance is provided to facilities
so that proceeds from the sale or exchange of unneeded equipment
are retained for use by the Department, (ii) strengthening controls
over the receipt and disposition of funds from the sale of personal
property, and (iii) establishing a more accurate reporting system
that reflects the results of property disposal activities. Appropriate
retention of sale proceeds could provide facilities with additional
funds that could be used to help support program operations.
In FY 1995, facility direct sales of excess, unneeded, and worn-out
equipment generated approximately $5 million in revenue which
could have been retained by VA, but instead was deposited to non-VA
miscellaneous receipts accounts with the U. S. Treasury. The
Deputy Assistant Secretary for Acquisition and Materiel Management
indicated agreement with the report recommendations and provided
appropriate implementation actions. We consider all issues resolved.
(Audit of VA's Excess Equipment Program)
Issue: Integrity of the Procurement Program
Conclusion: Investigations disclosed third party fraud in VA's procurement program.
Impact: Assurance of integrity of Government program.
Issue: Alleged Management Errors Related to a New VA Regional Office Construction Project
Conclusion: The contracting officer acted within his authority, although a less expensive system than funded was accepted.
Impact: Resolution improved VA outcome, including $100,000 credit to VA.
We reviewed allegations that VA had improperly accepted an alternate,
deficient skylight system as part of the construction of a VA
regional office, when VA already had funded a more expensive state-of-the-art
skylight. Congress, on behalf of a constituent, forwarded the
allegations to us for review. Our review showed that the VA contracting
officer acted within his authority in accepting the alternate
skylight system, and allowing deviations to the specifications
for credit. However, we also concluded VA had accepted a significantly
less expensive skylight than funded, that the skylight did not
meet additional specifications, and the consideration VA received
was not commensurate with the value of the deviations allowed.
As a result of the complaint and OIG's involvement in the issue,
the outcome for VA was improved significantly over what it would
have been otherwise. Although VA ended up accepting an alternate
skylight, VA obtained an additional $100,000 credit, a significantly
improved warranty, and a continued waiver of delay claims by the
general contractor. (Results of Review of Congressional Inquiries
Concerning Regional Office Skylight System Bay Pines, FL)
Issue: Suspected Construction and Renovation Fraud
Conclusion: Individual sentenced for submitting false affidavits.
Impact: Individual is held accountable for illegal acts.
A former senior underwriter for a firm which provided personal surety bonds for Federal projects was sentenced in U.S. District Court to 200 hours of community service and 36 months' probation. An investigation revealed that the underwriter prepared false affidavits of surety and submitted them as bonding on VA and U.S. Army construction projects.
Issue: VA's Consolidated Financial Statements for 1996 and 1995
Conclusion: Significant progress has been made to improve financial management in the Department, some reportable conditions remain.
Impact: Accurate reporting of financial information.
We audited the Department's Consolidated Financial Statements
for FYs 1996 and 1995. For FY 1996, VA reported assets totaling
$43.4 billion and expenses totaling $43.9 billion. Audit results
showed significant continued progress overall in improving financial
management during the year. We provided an unqualified opinion
on the September 30, 1996 year-end balances contained in VA's
Statement of Financial Position (i.e., balance sheet). This is
significant because it provides sound baseline information for
the future. However, we also found that the FY 1995 year end balances
and the FY 1996 statements of operations and changes in net position,
cash flows, reconciliation of excess (shortage) of revenues and
financing sources over total expenses, and budgetary resources
and actual expenses remain qualified to the extent prior property
and receivable errors affect the statements. The report also
discusses six reportable internal control weaknesses that expose
VA to significant risks and vulnerabilities if not addressed.
VA management needs to:
We reaffirmed the recommendations in our prior reports for previously
reported items where improvements are in process, and made new
recommendations to improve automatic data processing security
access controls and to strengthen Housing Credit Assistance Program
accounting.
Additionally, the report discusses one previously reported significant
nonconformance with the Public Law 96-466 requirement to charge
interest and administrative costs on compensation and pension
accounts receivable balances. VA needs to implement the law or
work with Congress to change the law if the law is not considered
appropriate.
The Assistant Secretary for Management (the Department's Chief
Financial Officer) stated he shared the audit results with the
financial managers in VHA, VBA, and National Cemetery Service,
and other interested VA staff and program managers. They indicated
general agreement with the audit results and plan to provide implementation
plans on their respective areas. We will follow up on the implementation
actions during our audit of VA's FY 1997 Consolidated Financial
Statements. (Audit of Department of Veterans Affairs Consolidated
Financial Statements for Fiscal Years 1996 and 1995)
Conclusion: Addition action is needed to improve financial management of benefits.
Impact: Improved VBA financial management.
As part of our audit of FY 1996 Consolidated Financial Statements, we tested VBA's C&P and education programs' account balances, selected transactions that affect the Consolidated Financial Statements, internal controls, and compliance with laws and VA regulations. Based on the audit test performed at VA's Hines Finance Center (HFC), Debt Management Center (DMC), and selected VAROs, we concluded that VBA staff generally established required internal controls for monitoring financial information, and generally complied with VA policies and procedures. However, additional actions were needed to correct or improve three conditions at the HFC, three other conditions at VA regional offices, and two other conditions at the DMC reported in prior audits. None of the issues materially affected the financial statements. We will follow-up during subsequent financial statement audits. (Management Letter -- Fiscal Year 1996 Financial Statements-Benefits Programs)
Conclusion: Management was correcting a number of system and control problems; however, other actions are needed to strengthen controls and improve financial management.
Impact: Financial statement opinion could not be provided pending implementation actions.
We were requested by the Office of Acquisition and Materiel Management
to audit VA's Supply Fund Statement of Financial Position as of
September 30, 1995. We found that management was correcting a
number of system and control problems, and we identified other
actions which could be taken to strengthen internal controls and
improve financial management. We disclaimed expressing an opinion
on the financial statements until these improvements are in place,
and sufficient, competent evidence is available to support the
accounts with material balances.
The Assistant Secretary for Management outlined actions to strengthen
the Supply Fund's internal control structure pertaining to accounting
adjustments, accounts receivable, accounts payable, equipment,
supply inventories, and cash. He also indicated that some of
the actions recommended had already been addressed and that a
strategy was being developed to address other shortcomings and
implement needed improvements. The actions taken and planned
are considered significant and should strengthen internal controls
and improve financial management. (Veterans Affairs Supply
Fund Statement of Financial Position as of September 30, 1995)
Conclusion: The VAMC was not in compliance with government purchase card procedures.
Impact: Advisory report.
As part of the Department's FY 1996 Consolidated Financial Statement
audit, we reviewed selected financial operations and tested internal
controls as they related to expenditures at one VAMC. The review
included a review of controls over the use and administration
of government purchase cards.
We concluded that internal controls were adequate to ensure the reliability of obligations as shown in the financial statements as of September 30, 1996. However, we identified a number of instances of noncompliance with government purchase card practices and guidelines in a number of areas, including cardholder accountability, maintenance of cardholder accounts, certification and documentation of cardholder statements, use of required sources of supplies and services, and proper use of funds and distribution of costs. We did not make any recommendations and issued an advisory report detailing our findings, with followup planned during future financial statement audits. (Advisory - Greater Compliance with Governmentwide Purchase Card Procedures is Needed)
Issue: Assessment of PAY-VA
Conclusion: Recommendations were made to assist with PAY-VA implementation.
Impact: Early review improved process to implement PAY-VA.
The purpose of the evaluation was to provide an early assessment
of the design, development, and implementation process for "PAY-VA",
VA's new payroll system. This information technology initiative
is estimated to have life-cycle costs of approximately $115 million.
System operating benefits are estimated at about $205 million,
primarily attributable to staffing reductions that will be achieved
by consolidating support services, eliminating redundant service
delivery functions, and fully leveraging technology.
We concluded that project managers had established management
controls over the multi-faceted details this system development
effort entails, and user involvement was significant. We identified
opportunities to enhance PAY-VA implementation efforts concerning
project documentation and workplans, cost information, contract
deliverables, system security, correction of identified materiel
weaknesses, training, and Contracting Officer's Technical Representative
duties. The Assistant Secretary for Management and the Assistant
Secretary for Human Resources and Administration agreed with the
report recommendations, provided responsive implementation plans,
and noted that our early review will be helpful in ensuring the
success of the initiative. (Evaluation of the Design and Implementation
of PAY-VA)
Issue: Integrated Funds Distribution, Control Point Activity, Accounting, and Procurement (IFCAP) System, Phase III
Conclusion: IFCAP was performing as designed with the exception of application and data security.
Impact: Identification of significant problems which increase the vulnerability of the system to unauthorized access.
IFCAP, an automated system supporting a variety of administrative activities, is used in the management and tracking of most of the $17 billion in VA funds allocated to medical care. We contracted for this audit to determine whether: (i) IFCAP, as installed at selected VHA sites, is performing as designed; (ii) security procedures are adequate to prevent inappropriate use, destruction, disclosure, or modification of the system and/or data within it; (iii) backup procedures are adequate to allow manual processing during any downtime and permit complete recovery and updating of appropriate system files upon return of the system; and (iv) assess whether installation of site modifications interfere with system requirements and/or controls.
The audit found that the IFCAP system is performing as designed,
with some exceptions, and that site-installed software modifications
do not adversely affect internal controls. However, significant
problems exist with the security procedures controlling access
to the IFCAP system and data within it, and with backup and recovery
procedures. In addition, application maintenance procedures employed
at many of the sites visited increase the vulnerability of the
system to access and modification without management's approval.
The Assistant Secretary for Management concurred with all recommendations. The Under Secretary for Health concurred with all but one recommendation, pending the results of an assessment by his management and development teams. Corrective actions were completed or implementation plans were provided for all other recommendations. We consider all issues resolved. (Audit of IFCAP System, Phase III)
Issue: Specialized Investigations Regional Task Force (SIRTF) Investigations
Conclusion: SIRTF investigations continue to disclose drug diversion, sales of controlled substances, workers' compensation fraud, and corruption.
Impact: Individuals are held accountable for illegal acts.
The SIRTF is an enforcement unit comprised of special agents from
the VA OIG and the VHA. Under the direct control of the VA OIG,
SIRTF became operational in the spring of 1994 and has successfully
investigated allegations of drug diversion; sales of controlled
substances; sales and possession of firearms; workers' compensation
fraud; and other criminal violations at VAMCs in the New York
Metropolitan Area.
SIRTF was created in response to concerns voiced by the directors
of three New York area medical centers over various criminal activities
at their facilities. The VA OIG's assistance was sought because
outside law enforcement agencies frequently were unable to lend
assistance. Federal agencies such as the Drug Enforcement Administration
and the Federal Bureau of Investigation have workloads and priorities
which often preclude addressing criminal activity at VAMCs; the
VAMC Security Police lacked the personnel and expertise to conduct
these investigations; and local authorities were unable or unwilling
to devote limited resources to what they perceived as a Federal
problem.
During the reporting period, the results of SIRTF investigations
were in three major areas: drug diversion and sales of controlled
substances, workers' compensation fraud, and corruption. The
following are examples of investigations.
Controlled Substances
Workers' Compensation Fraud
Corruption
Issue: Investigations of Misconduct and/or Illegal Acts by Employees and Third Parties
Conclusion: Instances of thief, embezzlement, bribery, fraud, conflict of interest, and other acts of misconduct were disclosed.
Impact: Individuals are held accountable for illegal acts.
Employee Theft/Use/Sale of Illegal Drugs
Theft and Embezzlement
Acceptance of Bribes, Kickbacks, Gratuities, Conflicts of Interest
Workers' Compensation Fraud
Destruction of Government Property
Employee Misconduct
Conclusion: Applicable regulations and policy guidance were met.
Impact: Assurance of integrity of Government requirements.
Conclusion: Several alleged conditions were substantiated, but willful misconduct or mismanagement as a cause was rarely disclosed.
Impact: Seven VA employees received or will receive disciplinary action; $90,000 potential Better Use of Funds; and $5,000 recovery.
During the period, we issued 20 special inquiry reports. Following
are summations of 8 of the more significant reports issued: