Audit of VA’s Green Management Program Solar Panel Projects

Report Information

Issue Date
Report Number
15-03688-304
VISN
State
Arkansas
District
VA Office
Acquisitions, Logistics, and Construction (OALC)
Office of Management (OM)
Report Author
Office of Audits and Evaluations
Report Type
Audit
Recommendations
4
Questioned Costs
$0
Better Use of Funds
$0
Congressionally Mandated
No

Summary

Summary
Senator John Boozman and Congressman French Hill of Arkansas requested the Office of Inspector General conduct a review of an $8 million, 1.8 million megawatt work-in-progress solar panel system at the John L. McClellan Memorial Veterans Hospital, Little Rock, AR. They also requested we review the planning and management of other VA solar projects. Our objective was to determine whether VA effectively planned and managed its work-in-progress solar photovoltaic projects to meet project timelines and expected project power generation goals. The Little Rock VA medical facility did not effectively plan the installation of a solar panel system. The system is not completed and is not generating solar power. The project experienced significant delays and additional contract costs due to disassembly of previously installed solar panel carport structures to accommodate a parking garage. As a result, the solar project is expected to be fully completed in January 2017, over 4 years beyond its original completion date, with unexpected costs of approximately $1.5 million. We reviewed 11 of 15 solar projects awarded from fiscal year (FY) 2010 through FY 2013 that were a work-in-progress as of May 2015. At the completion of our audit work in March 2016, only 2 of 11 solar projects were fully completed. In July 2016, VA informed us that 5 of 11 solar projects were fully completed. This occurred because of planning errors, design changes, a lengthy interconnection process, and contractor delays. As a result, VA did not increase renewable energy for those solar projects in the time frame planned and incurred additional costs through needed contract modifications. We recommended the Interim Assistant Secretary for Management implement additional controls to prevent solar panel conflicts, share best practices for executing timely interconnection agreements, implement power generation monitoring controls, and conduct lessons learned assessments. The Interim Assistant Secretary for Management concurred with the intent of two of the four recommendations and nonconcurred for the remaining two recommendations. The Interim Assistant Secretary for Management also provided additional comments, which we addressed in this report.

Open Recommendation Image, SquareOpenClosed and Implemented Recommendation Image, CheckmarkClosed-ImplementedNot Implemented Recommendation Image, X character'Closed-Not Implemented
No. 1
Closed and Implemented Recommendation Image, Checkmark
to Office of Management (OM)
We recommend the Interim Assistant Secretary for Management strengthen controls to ensure facility officials inform officials in the contracting office of potential conflicts between solar panel projects and other projects.
No. 2
Not Implemented Recommendation Image, X character'
to Office of Management (OM)
We recommended the Interim Assistant Secretary for Management identify and share best practices for executing timely interconnection agreements with utilities based on continued collaboration with other Federal agencies.
No. 3
Closed and Implemented Recommendation Image, Checkmark
to Office of Management (OM)
We recommended the Interim Assistant Secretary for Management implement controls to periodically compare actual and expected solar power generation data to ensure the solar panel system is performing as planned.
No. 4
Not Implemented Recommendation Image, X character'
to Office of Management (OM)
We recommended the Interim Assistant Secretary for Management conduct a lessons learned assessment for solar project delays and implement additional controls to ensure future solar panel projects are properly planned and managed.